Operational readiness is not the same as project completion
A service can be technically deployed and still be unsafe to operate. The readiness question is whether the receiving organisation can detect, understand, support, recover and govern the service when something happens after go-live.
What should a readiness checklist cover?
- Service scope, ownership and support boundaries are understood.
- Knowledge has been transferred, validated and tested through shadowing or rehearsal.
- Monitoring, alerting and event ownership are operational.
- CMDB and service relationships are sufficient for impact and support decisions.
- Incident, Major Incident, Change, Request and escalation routes are usable.
- Supplier interfaces, contacts and obligations are clear.
- Service levels and reporting can be measured from day one.
- Known risks, defects and workarounds have explicit owners.
- Go-live decision criteria and exception authority are defined.
- Early life support has entry, exit and handover criteria.
Use evidence, not confidence statements
Readiness should be demonstrated. A completed task is not evidence that an operational capability works. A stronger approach uses artefacts, tests, rehearsal outcomes, reconciled data and explicit acceptance criteria.
Focus on cross-functional dependencies
The highest transition risks often sit between workstreams. A CMDB dependency can affect monitoring, incident impact, service mapping and acceptance simultaneously. Treating those as separate project tasks can hide the real risk.